Project Schedule

MILESTONEAnticipated Timing
Design Phase (30%-90%)May-Aug 2026
Review of Design Documents/County & Town of Plattsburgh FeedbackLate May-Late July 2026
Draft Permits Submitted (NYSDOT, Clinton County DPW)July 2026
Submit Plans, Specs & Engineer’s Report to CCDOHLate August 2026
CCDOH Approval Received/Permits ApprovedOctober 2026
Final Plans & Specifications Complete (100%)October 2026
Advertise for BidsOct.-Nov 2026
Bid OpeningNovember 2026
Construction Contract AwardDecember 2026
Pre-Construction Meeting/Shop Drawing ReviewJanuary-April 2027
Construction StartApril 2027
Substantial CompletionAugust 2027
Final CompletionSeptember 2027

*Please note that these timeframes are approximate and may be refined as the project progresses, particularly as permitting and coordination efforts advance.