Project Schedule
| MILESTONE | Anticipated Timing |
| Design Phase (30%-90%) | May-Aug 2026 |
| Review of Design Documents/County & Town of Plattsburgh Feedback | Late May-Late July 2026 |
| Draft Permits Submitted (NYSDOT, Clinton County DPW) | July 2026 |
| Submit Plans, Specs & Engineer’s Report to CCDOH | Late August 2026 |
| CCDOH Approval Received/Permits Approved | October 2026 |
| Final Plans & Specifications Complete (100%) | October 2026 |
| Advertise for Bids | Oct.-Nov 2026 |
| Bid Opening | November 2026 |
| Construction Contract Award | December 2026 |
| Pre-Construction Meeting/Shop Drawing Review | January-April 2027 |
| Construction Start | April 2027 |
| Substantial Completion | August 2027 |
| Final Completion | September 2027 |
*Please note that these timeframes are approximate and may be refined as the project progresses, particularly as permitting and coordination efforts advance.